Capacity and performance ratio tests are essential tools used to validate the efficiency and reliability of photovoltaic (PV) systems for potential buyers, lenders, or investors. These tests help de-risk investments by providing a clear, data-driven assessment of how well a system performs compared to its expected design.
One widely recognized standard for this process is ASTM E2848-13, "Standard Test Method for Reporting Photovoltaic Non-Concentrator System Performance." This test compares the actual performance of a PV system with its modeled output, ensuring that the real-world results align closely with expectations—within acceptable margins of error. By following a standardized procedure set by a reputable committee, stakeholders can trust that the evaluation is fair, consistent, and reliable.
**Why does this matter for project owners and financiers?**
Failure to meet the test criteria or delays in completing the process can have financial consequences. For instance, if the test isn't passed on time, it could trigger liquidated damages under the project's contractual agreements. Therefore, timely and accurate testing is crucial to avoid costly setbacks.
**How is the test performed?**
While the concept seems simple, the execution involves detailed calculations and careful data handling. Here’s a step-by-step breakdown:
**Step 1: Gather Inputs**
To ensure a smooth testing process, you must prepare the following:
- A validated PVSYST model.
- Experience in regression modeling and access to a test sheet.
- A fully operational system with properly functioning equipment and calibrated weather stations.
- At least 5–7 days of continuous operation to collect sufficient data, though weather conditions may extend this period.
**Step 2: Export Data**
Once the inputs are ready, gather and organize the necessary data:
- Extract annual raw data from your PVSYST model, including GHI irradiance, ambient temperature, wind speed, POA correction factors, and timestamps.
- Retrieve climate and performance data from your data acquisition system, including date/time stamps, production meter readings, temperature, wind speed, and POA irradiance.
- Review mechanical and electrical drawings to identify any potential issues such as shading or inverter clipping that might affect performance.
**Step 3: Filter the Data**
This stage is often the most complex, as it involves cleaning and refining the dataset:
- Ensure at least 50 fifteen-minute data points (or 750 minutes of data).
- Exclude data below 400 W/m² and ensure the system operates above 98% of the inverter's nameplate capacity.
- Keep POA irradiance within a ±20% range.
- While there are no strict limits on temperature or wind data, they should be excluded if they don’t correlate with system performance.
**Step 4: Run the Regression**
Use statistical methods to analyze the data and determine the power capacity and standard error. If the measured-to-modeled ratio exceeds 95% and the regression error remains under 5%, the test is considered successful.
**Common Challenges**
If the results aren’t favorable, consider these common issues:
- It may take longer than expected to collect enough high-quality data, especially depending on the season and system design.
- The PVSYST summary report is not sufficient; you need detailed hourly data.
- Improper setup during the first attempt can lead to errors, even if the ASTM method is followed.
- Poorly calibrated sensors can significantly impact accuracy, so calibration is critical before data collection.
**Who conducts this test?**
Given the complexity, many project owners turn to specialized third-party engineers. Pure Power offers an Owners Engineering team that specializes in ASTM E2848 and other performance verification tests. As an independent party, we ensure the analysis is conducted thoroughly and accurately, following all industry standards. Our goal is to provide transparent, reliable results that support informed decision-making for all stakeholders.